‘Desperately needed’ hospitals delayed due to Carillion collapse

ENGINEERING giant Carillion’s collapse will delay the construction of two “desperately needed” hospitals for several years, an official report found yesterday.

The 646-bed Royal Liverpool, which was set to open in 2017, is forecast to be completed more than five years late, according to the National Audit Office.

With no opening date set, it is now predicted the hospital will cost more than £1 billion to build and run, compared with an original cost of £746 million, said the NAO.

The 95th Anniversary Appeal
Support the Morning Star
You have reached the free limit.
Subscribe to continue reading.
Similar stories
FRAUGHT PROCESS: A member of HS2 staff walks through the Chilterns tunnel of the new line
Features / 23 May 2026
23 May 2026

The HS2 debacle exposes what happens when public infrastructure is handed to private contractors – especially when set against China’s state-led high-speed rail success, says CARLOS MARTINEZ

Business / 7 January 2026
7 January 2026